StocksMedium•19 October 2026•
4 min read

Digital Realty Continues Building About $3 Billion Campus After White Phosphorus Removal

By

Key Facts

1Total proposed investment in the Fort Gillem project is about $3 billion.
2The project budget includes more than $100 million for remediation and environmental work.
3The campus is designed to support an initial IT load of 212 megawatts.
4The company expects the first phase to open in early 2028.

Construction continues at Digital Realty's Fort Gillem data center campus, with a proposed investment of about $3 billion, according to an investigation published by Hunterbrook in October 2026 and the company's official project estimates. The discovery of white phosphorus at the site prompted a temporary halt to work in the area where it was found, while construction continued across the campus. The incident occurred in December 2025, before the investigation renewed attention on development and environmental remediation at the site. The company said the material was removed and taken to a licensed hazardous waste treatment facility, and that no injuries were reported from the incident. The project is being built on a site with a history of contamination linked to past activities at Fort Gillem, which was subject to regulatory intervention by the U.S. Environmental Protection Agency.

The project budget already includes more than $100 million for site remediation and environmental work, according to Digital Realty's official project page. Planned work includes addressing the development's effects on waterways, as well as methane remediation and stabilization of soil and bedrock at the site. The proposed development covers 97 acres, according to the company's published campus specifications. The proposed floor area is approximately 1.9 million square feet under the plan to build the Fort Gillem data center campus. The campus is designed to support an initial IT load of 212 megawatts, according to figures in the company's project presentation.

Formal environmental intervention at the former base dates back to September 24, 2014, when the U.S. Environmental Protection Agency issued an order requiring the Army to take corrective measures at Fort Gillem. The agency documented contamination of soil, sediment, surface water and groundwater resulting from the base's past activities. The order required the identification of private drinking water wells and springs in the area surrounding the former military site. It also required the Army to assess whether those wells and springs could contain hazardous contaminants as part of the testing required at the time. The agency said the Army had collected air samples from 56 homes and businesses when its statement was issued, with testing expected to expand to additional properties.

The reasons for the regulatory intervention at the time included the Environmental Protection Agency's objections to how the Army conducted a vapor intrusion study linked to the site. The agency said the Army had "deviated significantly from the approved work plan for the study," contributing to its decision to issue the corrective measures order. The measures required at the time covered air testing in homes and businesses, as well as assessments of private drinking water sources surrounding the base. As part of the former base's redevelopment, the agency later documented building demolition and site preparation work during 2015. That work was carried out as part of the development of Gillem Logistics Center, at an earlier stage of the reuse of the base's land.

At the company level, Digital Realty's global network comprises more than 300 facilities, according to its investor relations statement announcing the date of its next earnings release. Those facilities span more than 55 metropolitan areas, while the company's geographic footprint extends to more than 30 countries. In the second quarter of 2026, net income available to common shareholders was $1.21 per share. That compares with $2.94 per share in the corresponding period of 2025, according to the company's quarterly earnings statement. Funds from operations, meanwhile, rose to $2.73 per share in the second quarter of 2026, compared with $1.75 per share in the corresponding period of 2025.

The official project page sets early 2028 as the expected opening date for the first phase of the Fort Gillem campus. Digital Realty expects that phase to support about 60–75 permanent jobs upon completion. The company describes the anticipated roles as "high-quality permanent jobs" in its presentation of the project's expected economic impact. Ahead of the expected opening, the company will announce its next quarterly results on October 29, 2026, according to its investor relations statement. The announcement is scheduled for after the market closes that day.