Woodside resumes work on $12.5 billion Scarborough project after Greenpeace protest

By

Key Facts

1Woodside's chief executive described the Scarborough project as worth US$12.5 billion.
2The Scarborough project is more than 98% complete, excluding Pluto 1 modifications.
3The project's total design capacity is 8 million tonnes of LNG a year.
4Woodside confirmed on Monday that commissioning work on the floating production unit had resumed after the protest.
5Woodside targets its first LNG cargo from Scarborough in the fourth quarter of 2026.

Woodside has resumed commissioning work on the floating production unit at its Scarborough gas project following a halt after a protest by Greenpeace activists, a company spokesperson confirmed to LNG Prime on Monday. The resumption concerns a project that the company's chief executive described as a US$12.5 billion investment in a speech published by Woodside about its operations. The company had announced the suspension of pre-commissioning work at Scarborough as part of standard procedures following unauthorised access to the facility, according to a statement reported by the Australian Broadcasting Corporation. Confirming the return to work, the spokesperson said: "Woodside has resumed commissioning activities on the Scarborough floating production unit." The activities resumed after a protest at the facility as the company works to complete its liquefied natural gas project.

Greenpeace Australia Pacific said 4 activists took part in climbing and occupying the Scarborough facility, in an action the organisation linked to other Woodside oil and gas plans. In its statement, it said the protest opposed the company's plans to drill near Scott Reef under the proposed Browse development. The organisation thus identified Browse as the project whose plans it opposed, while its activists staged their action inside the company's Scarborough facility. In a subsequent statement on the continuing protest, Greenpeace said two activists had set up temporary suspended tents on the facility's southeastern support column. The organisation described the activists' position as being on a support column of the floating production unit, after its initial statement outlined the group's participation in climbing and occupying the site.

During the operation to end the protest, specialist police arrived at the floating production unit by helicopter at around 11:30 a.m. Western Australia time, according to a Greenpeace statement on the activists' detention. The developments subsequently moved to court, with the Australian Broadcasting Corporation reporting that the two men were granted conditional bail. Woodside, for its part, criticised the protest and the measures required to address the entry into the facility, in a statement reported by Investing. The company said Greenpeace's actions "required a significant, potentially costly response that was entirely avoidable." In its statement, Woodside linked the organisation's action to the scale of the response it required, describing the cost as a possibility in its objection to what happened at the site.

On construction progress, Woodside's official project page says Scarborough is more than 98% complete, excluding Pluto 1 modifications from that estimate. That compares with completion of 96% reported by the company in its first-quarter report, before the progress outlined in the subsequent update on its page. In July, the floating production unit reached the ready-for-start-up milestone, according to a presentation published by Woodside on progress. The same month saw first gas flow from the Scarborough field, a development milestone the company listed alongside the floating unit's readiness. These operational milestones place the protest and resumption of work in the context of completing the project's facilities, following its advance from the completion level announced in the quarterly report to its latest level.

Scarborough's design LNG capacity is 8 million tonnes a year, according to Woodside data published on the project's official page. The company presents this capacity on a whole-project basis as part of its LNG production specifications. The field development plan includes 8 wells at readiness for operations, according to a company presentation filed with the U.S. Securities and Exchange Commission. The planned number rises to a total of 13 wells over the field's life, distinguishing the initial well programme from the development programme extending throughout its life. Alongside LNG capacity and the well plan, the same presentation includes a new domestic gas plant with design capacity of 225 terajoules a day among the facilities the company lists in the project development.

Woodside's disclosure calendar sets 21 October for the release of its third-quarter report, according to the schedule in its first-quarter report. The date follows the company spokesperson's announcement that commissioning work had resumed on the floating unit, making it the next quarterly disclosure on its announced schedule. For LNG deliveries, Scarborough's official page sets the fourth quarter of 2026 as the target for the project's first cargo. This date represents the company's target for the first shipment, within the schedule it publishes alongside construction progress and design capacity data. On the protest's legal proceedings, the Australian Broadcasting Corporation reported that the case was adjourned until 4 December at Perth Magistrates Court to obtain legal advice.