Microsoft pulls out of deal for 50-megawatt data centre in Britain

By

Key Facts

1The Loughton data centre plan targeted 50 megawatts of AI computing capacity, expandable to 90 megawatts.
2The original plan called for delivery of 23,040 graphics processing units in the first quarter of 2027 to support Microsoft Azure services in Britain.
3Grid officials told Nscale that electricity supply to the Loughton site was not expected until the 2030s.
4Microsoft said the withdrawal decision relates to a single site and that it remains committed to its partnership with Nscale.

Microsoft has withdrawn from a deal to lease computing capacity at a data centre being developed by Nscale in Loughton, Essex, Britain, according to the Wall Street Journal. The withdrawal followed delays in supplying electricity to the site, a project intended to provide AI computing infrastructure. Reuters reported that grid officials told Nscale they did not expect to supply power to the site until the 2030s. The developer had announced a design providing 50 megawatts of computing capacity. The original plan included scope to expand that capacity to 90 megawatts, according to Nscale's project announcement.

The Loughton plan called for hosting 23,040 Nvidia graphics processing units to support Microsoft Azure services in Britain, according to Nscale. The company originally set the first quarter of 2027 for delivery of the processors, ahead of the date it was subsequently told to expect electricity at the site. Commenting on the withdrawal in remarks reported by the Wall Street Journal, Microsoft said it "remains committed to its partnership with Nscale, and the decision relates to a single site". The company thus maintained the broader partnership while ending the agreement to lease computing capacity in Loughton. Nscale, for its part, said it was "exploring alternative power sources for the site", according to a spokesperson quoted by Data Centre Dynamics.

The broader partnership includes an agreement previously announced by Nscale to deploy about 200,000 Nvidia graphics processing units across Europe and the United States. Its plans include supplying about 52,000 processors to Microsoft from a computing campus in Narvik, Norway, according to the developer's announcement. In Britain, Microsoft announced a $30 billion investment plan spanning 2025 to 2028. That plan covers AI infrastructure and the company's operations, according to Microsoft's announcement. The group allocated $15 billion of that total to capital expenditure to build cloud and AI infrastructure in the British market.

The withdrawal from the Loughton agreement comes after Nscale filed for an initial public offering in the United States, according to Reuters. The agency said the filing took place in the month before its report on Microsoft's withdrawal from the British site agreement. Nscale previously raised $1.1 billion in a Series B funding round, according to the company's funding announcement. The round was led by Norway's Aker, which headed the investors participating in the fundraising. Nvidia also participated, alongside Nokia, Point72 and T Capital, according to the names listed in Nscale's announcement.

Across Britain's grid, energy regulator Ofgem says applications for electricity connections to serve demand surged in less than a year. The capacity represented by those applications rose from 41 gigawatts to 125 gigawatts, according to the regulator's statement. Its regulatory consultation points to about 73 gigawatts of data centre applications in the electricity connection queue. To address these applications, Ofgem proposes imposing a fee to demonstrate the commitment of data centre projects seeking connections. The proposal also includes mandatory progress milestones to manage those projects' positions in the queue, according to the consultation document on connection reforms.

The evidence of progress proposed by Ofgem includes proof of a credible end user for the data centre as part of the requirements for managing the connection queue. The proposal makes this proof part of the regulatory procedures under consideration for data centre projects applying for electricity connections. The consultation on the proposed reforms has closed, according to the status published on the regulator's website. Those reforms now await a regulatory decision, while Nscale continues to seek alternatives for supplying power to the Loughton site. On the upcoming corporate calendar, Microsoft reports its financial results on 28 October 2026, according to the company's investor relations website.