StocksMedium•20 October 2026•
4 min read

Soar AI forecasts revenue of $175 million to $200 million in 2027

By

Key Facts

1The company expects revenue of $175 million to $200 million during 2027 from contracted orders.
2The two orders have a total contractual value of $1.17 billion.
3An agreement with an institutional investor allows the sale of up to $1 billion in common stock, without obligating the company to use the facility.
4The Ohio site has 154 megawatts of available electrical capacity, with a roadmap to reach 480 megawatts.

Soar AI said in an update on its Ohio AI computing campus project that it expects revenue of $175 million to $200 million during 2027 from contracted orders. The estimates are based on contractual pricing and expected service commencement dates. The company aims to bring the first batch of processing units into service on December 31, 2026. It expects contractual revenue to begin in January 2027, subject to delivery and customer acceptance. The target date applies to bringing the first batch online, while deployment of the other computing units extends into later phases.

The deployments are underpinned by two orders from a major AI customer, according to the company's disclosure of the commercial agreement. Each order has a term of 4 years on a "take-or-pay" basis. The two orders have a total contractual value of $1.17 billion over the contract terms. Their terms include advance payments of about $133 million, of which about $40 million is due following the signing of the first order. The services agreement provides termination rights in the event of a material breach that remains unresolved after written notice and a 30-day cure period. Termination rights also cover specified bankruptcy or insolvency events, according to the company's filing with the U.S. Securities and Exchange Commission.

On site preparation, the company said the substation and medium-voltage power distribution systems were operational and had been commissioned and certified. This also included turbine-powered backup power systems, with the company describing the equipment as "operational and certified." Installation of data hall transformers and cooling equipment has begun as part of preparations to receive the computing units. The cooling design delivers liquid directly to the racks, with heat discharged through the plant's existing water network. The company said the design provides year-round free cooling. According to its statement on financing the expansion, the Ohio site has 154 megawatts of available electrical capacity, with a roadmap to reach 480 megawatts.

To finance the expansion of its infrastructure platform, the company signed an agreement with an institutional investor allowing it to sell up to $1 billion in common stock. The company controls drawdowns under the facility and is under no obligation to use it, according to its statement on the agreement. Share sales are subject to the filing of a resale registration statement and its being declared effective by the U.S. Securities and Exchange Commission. The agreement prohibits the investor's ownership from exceeding 4.99% of outstanding common stock. Without shareholder approval, issuances under the facility are limited to 19.99% of the shares outstanding when the agreement was signed. Use of the available financing is therefore subject to the registration procedures and ownership and issuance limits set out in the agreement.

Volato entered the AI infrastructure business after completing its merger with Alignment Engine, according to the statement announcing the transaction's completion. The company continued its aviation software operations alongside its entry into the new business. The project is located at a leased site in Ohio, where power, water and water treatment infrastructure was already operational when the merger's completion was announced. In its rebranding statement, the company said the Soar name refers to sovereign AI resources. Its stated strategy is to give customers greater control over their data, models and computing environments.

The next deployment phase includes a batch of 4,032 next-generation AMD graphics processing units, according to the project update. Soar AI plans to deploy these units on the chip supplier's Helios platform. It aims to have the data hall ready to receive the batch in February 2027. That date concerns preparing the hall to receive the equipment under the next phase's implementation schedule. The company set June 30, 2027, as the contractual date for bringing that batch into service.