i-80 Gold Posts Quarterly Loss of $48.4 Million as Development Costs Rise
Key Facts
i-80 Gold reported on November 2, 2026, that its net loss widened to $48.4 million in the third quarter from $41.9 million in the same period of 2025, while loss per share was $0.06, compared with $0.05. The company said the wider loss was primarily tied to higher pre-development, evaluation and exploration expenses, which rose to $33.355 million from $20.062 million. It attributed part of the increase to drilling programs at Ruby Hill, partly offset by lower revaluation expenses. Revenue, meanwhile, rose to $32.7 million from $32.0 million despite a decline in the volume of gold sold. The results reflected the impact of a higher realized gold price on revenue and gross profit, as development and exploration spending increased.
The company sold 7,744 ounces of gold in the quarter, compared with 9,368 ounces a year earlier, while the average realized price rose to $4,211 an ounce from $3,412. i-80 Gold said gross profit was $5.0 million, compared with $3.1 million in the year-earlier quarter, attributing the improvement to the higher realized gold price. Adjusted loss nevertheless widened to $48.2 million from $34.3 million, which the company linked to higher pre-development, evaluation and exploration expenses. The company used $32.541 million in operating activities during the quarter, compared with $15.246 million a year earlier. It said increased development and exploration spending lifted cash used in operations, while higher gross profit partly offset the impact.
Cash and cash equivalents totaled $411.4 million on September 30, down $53.2 million from June 30. The company said the decline was primarily due to $32.5 million used in operations and capital expenditures of $15.0 million. Capital spending was tied in particular to the start of refurbishment at the Lone Tree plant, whose 2026 capital costs the company expects to be below its original guidance. An engineering study in December 2025 estimated total refurbishment capital at $430 million, including a contingency of about 12%. The plan is to use the plant to process underground mine material, enabling a shift from third-party processing to processing at a company-owned facility.
i-80 Gold completed 760 meters of underground development at the Archimedes project during the quarter and said the start of production mining in the upper portion remains targeted for the fourth quarter of 2026. The company, however, expects consolidated gold production for 2026 to come in at the lower half of its guidance range. It attributed this partly to the decision to heap-leach Archimedes oxide ore at its leach pad rather than sell it, delaying the recording of its production from the fourth quarter of 2026 to the first quarter of 2027. More than 6,200 recoverable ounces were in material being processed at a third-party facility on September 30, it said. The company expects to process more than half of that material by the end of 2026 and listed “first gold poured” from Archimedes among its fourth-quarter catalysts.
The company said operating costs, sustaining capital, growth capital and pre-development expenses are expected to be at the lower end of their guidance ranges, while exploration spending will be below plan for 2026. It attributed the expected reduction in exploration spending to fewer meters drilled, labor shortages and rig availability earlier in the year. At Granite Creek, mining activity during the quarter was affected by contractor employee turnover amid increased competition for skilled underground labor. The company said the contractor later increased staffing to align labor with the mining rates required for the rest of 2026. It also said the Lone Tree facility is equipped to process material from Granite Creek and Archimedes, followed in the future by material from the Cove project. Management is scheduled to discuss the quarterly results and project activity on a call on November 3, 2026, at 10:00 a.m. Eastern time.