1The agreement to buy industrial properties in Yadkin County is set at $60.0 million in cash.
2Expected initial capacity at the two sites is at least 60 megawatts, with potential to reach about 200 megawatts within 7 years.
3WhiteFiber is targeting initial service readiness at the two sites in late 2027.
4The company announced a $865 million contract to operate 40 megawatts for Nscale on October 27, 2026.
5WYFI shares closed at $9.26 on November 2, 2026.

WhiteFiber disclosed in August an agreement to buy industrial properties in Yadkin County, North Carolina, for $60 million in cash through its subsidiary Enovum Data Centers Corp. The company said the two sites could provide combined initial capacity of at least 60 megawatts after development. Potential capacity could reach about 200 megawatts within seven years of closing, subject to confirmation of capacity and power availability. WhiteFiber is targeting initial service readiness at the two sites in late 2027. The purchase could not be verified through an open official filing, so the amount and capacity figures remain part of the announced agreement and plans.

The properties are about 55 miles from the company’s NC-1 campus in Madison and include about 120 acres and 500,000 square feet of existing warehouses, according to WhiteFiber’s description. The existing space provides a physical base for developing data center sites, while the stated capacity depends on power availability and confirmation. The company said development spending plans will align with final customer agreements and financing. The transition from land and buildings to operating capacity therefore remains contingent on those arrangements. The company did not specify a detailed timetable for capacity additions in the available information.

WhiteFiber said it had received non-binding letters of intent from prospective power customers for NC-2 and NC-3, as well as for expansion at NC-1. It added that it was in advanced discussions about these opportunities. The letters signal initial interest, but do not amount to final contracts to operate the sites or reserve their capacity. The company tied development spending to final customer agreements, making progress in the discussions relevant to its execution plans. The available information did not state the value of potential contracts or when they might be signed.

In its update on NC-1, the company said the capital investment required to deliver the initial contracted deployment was largely complete. It also expected total development costs to remain within the initial budget. It was still completing documents and requirements to close financing for NC-1, without guaranteeing that it would be completed. The update links progress on the existing project with plans to expand infrastructure at the new sites, but the company did not provide a budget figure or financing amount in the information provided. This comes as it seeks to align spending on NC-2 and NC-3 with agreements and financing.

WhiteFiber announced on October 27 a $865 million contract to operate 40 megawatts for Nscale. The contract provides context for the company’s data center infrastructure hosting business, but covers contracted capacity and does not change the fact that planned capacity at NC-2 and NC-3 remains subject to development and power availability. WYFI shares closed at $9.26 on November 2, according to EL7 daily data. The available data do not link that close to the property announcement or developments at NC-1. WhiteFiber is scheduled to report third-quarter results on November 10, 2026, with additional financial and operational updates, according to the company.