Riot lifts data center contracts to 1,151 megawatts, with nearly $38 billion in contracted revenue

By

Key Facts

1Contracted capacity across data center agreements reached 1,151 megawatts, with nearly $38 billion in contracted revenue.
2The Corsicana contract covers 910 megawatts and runs for 15 years.
3Riot estimates the initial value of the Corsicana contract at about $28 billion, potentially rising to about $54 billion with both extension options.
4Riot expects to deliver 400 megawatts at Corsicana in September 2027.

Riot Platforms said its three data center contracts cover 1,151 megawatts and represent nearly $38 billion in contracted revenue, after the Corsicana contract took effect on November 4, 2026. CEO Jason Les said the company expects the contracts to generate more than $2 billion in average annual net operating income once fully operational. The new contract adds the entire Corsicana site to the company’s portfolio through a power-backed land lease for Frontier AI’s lab. It covers 910 megawatts of critical IT capacity on a contiguous 332-acre plot. Riot said the initial lease term is 15 years, in an agreement that expands its shift toward leasing data center infrastructure.

Riot estimates the initial total value of the Corsicana contract at about $28 billion, with average annual rent of about $1.8 billion. Total value could rise to about $54 billion if both extension options, each lasting five years, are exercised. The company says the contract’s net operating income margin is nearly 99%, with average annual net operating income of nearly $1.8 billion over the initial term. The estimate is based on a triple-net lease, under which the customer bears taxes, insurance, site expenses and the cost of electricity consumed. Riot will build and maintain the power and site infrastructure, according to its disclosure.

The company estimates Corsicana’s capital requirements at about $6 million per megawatt of IT capacity, or $5.5 billion in total. It said this capital intensity is about half that of a typical Tier III construction project. Riot plans to deliver the project in three phases, beginning with 400 megawatts in September 2027. A further 200 megawatts is scheduled for delivery in January 2028, followed by 310 megawatts in July 2028. Rent for each phase will begin no later than 60 days after delivery of its power platforms, according to the company’s schedule.

The Corsicana contract is part of a broader expansion of contracted capacity that previously included two projects in Rockdale. In August 2026, Riot announced an initial 20-year contract to provide 191 megawatts, with delivery expected in two phases in December 2027 and June 2028. The company also signed its first contract with AMD in January 2026 to provide 25 megawatts in Rockdale for an initial term of 10 years. Riot’s filings say development of its data center leasing business began in 2025, drawing on its experience in power optimization, land acquisition, engineering design and construction execution. These steps link the company’s assets and operating expertise with long-term contracts to provide sites and power for data centers.

Riot’s third-quarter 2026 results showed revenue of $181 million, up 1% year over year. The company reported net income of $4 million and diluted earnings per share of $0.01, while adjusted EBITDA reached $191 million. Liquidity at quarter-end was $950 million, including $748 million in cash and $202 million in bitcoin. In its data center business, Riot recorded recurring operating lease revenue of $8.3 million at an 80% gross margin, as well as $10.2 million from tenant fit-out services. The company began reporting data center operations as a reportable segment in the first quarter of 2026, so no comparison with the same period a year earlier is available.

Riot shares closed at $15.37 on November 4, 2026, according to EL7 data. The Corsicana contract was signed on October 28 and became effective and binding on November 4 after its conditions were met. The company says its AMD, Rockdale and Corsicana contracts lift contracted capacity to 1,151 megawatts, and that full operation of these contracts could generate more than $2 billion in average annual net operating income. Future revenue depends on phase delivery dates and lease commencement, while the announced Corsicana schedule runs through July 2028. The expansion is therefore on a phased execution path, with the first delivery scheduled for September 2027.