Bernstein Cuts IREN Target to $55 From $100 Amid Texas Concerns

By

Key Facts

1Bernstein cut its IREN target to $55 per share from $100 on November 4, 2026.
2Data center projects tracked by ERCOT exceeded 400 gigawatts by November 4, 2026.
3Texas accounts for 25% of planned data center capacity in the United States.
4Bernstein used a 12x multiple of one-year forward 2030 EBITDA to value hosting businesses.

On November 4, 2026, Bernstein cut its price targets for seven Bitcoin mining companies expanding into data center and AI businesses, after Gina Hinojosa’s election as Texas governor raised concerns about the future of approvals in the state. The largest announced cut was for IREN, whose target fell to $55 per share from $100. The revisions covered Riot Platforms, MARA, CleanSpark, Cipher Mining, TeraWulf and Core Scientific. The review came as Hinojosa said she wanted to halt data center activity until measures to protect residents are adopted. Bernstein linked the new valuations to the hosting and power sector on which miners’ plans to move into AI businesses depend.

Bernstein cut its Riot Platforms target to $18 per share from $35, and its MARA target to $10 from $17, while lowering its CleanSpark target to $11 from $24. It also cut its Cipher Mining target to $15 from $23, and its IREN target to $55 from $100. The firm lowered its TeraWulf target to $20 from $36, and its Core Scientific target to $19 from $32. These targets cover the seven companies in the revision Bernstein announced on November 4. The cuts reflect a reassessment of opportunities to expand AI hosting capacity amid uncertainty over power and new grid connections in Texas.

Bernstein said it had lowered its valuation of the space and power leasing businesses for AI data centers, and applied a 12x multiple to one-year forward 2030 EBITDA. The firm described its approach, saying it “now values AI hosting businesses at 12x one-year forward 2030 EBITDA.” This valuation makes hosting activity one of the factors shaping the mining companies’ targets, alongside their Bitcoin-related businesses. Bernstein said more than half of the power capacity owned or planned by the companies it covers is in Texas. This leaves their plans particularly sensitive to any changes in the state’s approval and power policies.

Texas had begun restrictive steps before Hinojosa’s victory: on September 21, 2026, Governor Greg Abbott directed the state’s environmental agency to halt data center permits until ERCOT’s review was complete. Abbott said data center projects should cover the costs of electrical infrastructure and not raise residential electricity bills, and called for protection of local water resources. He also said his administration would work with the next legislature to eliminate financial incentives for the sector. This earlier trajectory adds context to Hinojosa’s pledge to halt activity in the sector until measures to protect residents are in place. At the same time, the issue goes beyond an anticipated political change, following an earlier review of permits and infrastructure.

Expansion plans face a large volume of demand for the grid: Reuters reported that the Texas grid operator was tracking more than 400 gigawatts of data center projects seeking to connect by November 4, 2026. The agency described this volume as close to what would be needed to power the entire southern United States. A Goldman Sachs note, as reported by Reuters, estimated that Texas accounts for 25% of planned U.S. data center capacity. This share helps explain the state’s importance to companies building new businesses around power and dedicated computing space. It also makes potential permitting or connection delays relevant to their project execution outlook.

Still, Bernstein sees the restrictions as potentially valuable for some companies that have already secured approved power capacity. The firm said companies such as IREN, Riot and Cipher could benefit if new restrictions make it harder to obtain grid connections. Bernstein estimates that the approved capacity these companies hold could become scarce and valuable. This possibility distinguishes projects still awaiting approvals from capacity already in place. The outcome remains tied to what restrictions the state adopts and how difficult it becomes to obtain new connections.

In the broader market, Nasdaq-100 futures fell about 1.5% overnight as election results emerged, before recovering on Wednesday morning, according to CoinDesk. In the November 5, 2026 session, CleanSpark closed at $5.68, MARA at $5.88, while Riot Platforms ended trading at $14.76. These closes came after Bernstein announced its targets on November 4 and provide an indication of share prices in the following session. Comparing a closing price with a price target does not mean either was reached or that the revision determines the stock’s direction. The published targets remain Bernstein’s revised estimates of the companies’ businesses amid regulatory and valuation risks.

Reuters reported that some data center projects in Texas could be delayed or their developers could leave the state, while others are expected to accelerate construction and operations before new restrictions take effect. The agency quoted a data center company adviser as saying the new administration and legislature would need to understand existing procedures and regulations before establishing a new set of laws and rules for the sector. The Associated Press also noted that Hinojosa’s agenda will face a divided legislature: Republicans lost the state House but retained control of the Senate. Hinojosa is due to take office in January 2027, according to AP. This places the transfer of power and the next legislative session at the center of the path data center companies and their analysts will be watching.