QatarEnergy in talks to buy 2 million tonnes a year from Rio Grande’s Train 6

By

Key Facts

1NextDecade shares closed at $5.85 on November 5, 2026.
2RGLNG Train 6 filed its permit application with the federal commission on May 26, 2026.
3The federal commission issued a notice of its intent to prepare an environmental impact statement on July 29, 2026.
4Train 6’s expected production capacity is about 6 million tonnes a year.
5Guaranteed commercial operation dates for Trains 1 to 5 range from late 2027 to the first half of 2031.

QatarEnergy is in advanced talks to buy up to 2 million metric tonnes a year of liquefied natural gas from Train 6 of NextDecade’s Rio Grande project, Reuters reported on November 6, citing two people familiar with the matter. The potential volume would account for part of the train’s capacity, which NextDecade estimates at about 6 million tonnes a year when operational. The report did not say a final agreement had been reached, leaving the matter in negotiations despite their advanced stage. The Qatari company’s interest in the unit comes as it seeks to secure supplies from a new U.S. LNG project. NextDecade shares closed at $5.85 in the November 5 session, according to EL7 data.

Train 6 is a planned expansion of the Rio Grande facility in Cameron County, Texas, involving a new liquefaction unit and a new marine berth, according to the U.S. Federal Energy Regulatory Commission’s classification. The commission lists the project as being in the “application filing” stage, which precedes the permits required for construction and operation. RGLNG Train 6 filed its application with the commission on May 26, 2026, seeking authorization to site, construct and operate the expansion project, according to NextDecade. Commercial talks are therefore under way over supplies tied to a project that must complete its regulatory process before moving to execution. This stage does not provide a start date for shipments from Train 6 to buyers.

The expansion’s review process dates back to November 2025, when the company asked the Federal Energy Regulatory Commission to begin pre-filing review. On July 29, 2026, the commission issued a notice of its intent to prepare an environmental impact statement for the project, part of the regulatory process before it rules on the application. The timeline shows that the formal permit application filed in May followed the start of pre-filing procedures, while the commission continued to classify the expansion as being in the application stage. This process makes the timing of potential supplies dependent on progress in the project’s reviews and approvals, as well as on commercial negotiations. Available information does not specify when these reviews will be completed or when a final permit decision will be issued.

NextDecade estimates Train 6’s expected production capacity at about 6 million tonnes a year, the project’s full capacity when operational, according to the company’s annual filing. The volume QatarEnergy is considering buying is up to 2 million metric tonnes a year, according to the sources cited by Reuters, representing part of the train’s expected capacity. The company began pre-filing procedures for Train 6 with the federal commission in November 2025, according to the same filing. Stating the production capacity does not mean the project has reached a final investment decision or that production is imminent. The potential Qatari volume remains subject to the parties reaching an agreement and the project completing its development and approvals.

Train 6 is being developed as NextDecade continues work on Trains 6 to 8 and their related permitting procedures, according to its quarterly report. For comparison within the project’s timeline, the guaranteed commercial operation dates for Trains 1 to 5 range from late 2027 for Train 1 to the first half of 2031 for Train 5. Those dates apply to the first five trains and do not set a schedule for Train 6. The difference highlights that the new supply talks relate to an expansion beyond the units for which the company has reported commercial operation dates. Reuters’ report did not give an expected start date for Train 6 production or delivery of the volumes under discussion.

QatarEnergy’s interest in U.S. supplies, as reported by Reuters, is linked to a broader strategy to secure revenue sources in the event that exports through the Strait of Hormuz are disrupted in the future. The chief executive said U.S. supply deals are intended to generate revenue if such a disruption occurs, without the report linking these talks to a completed agreement. The statement places the negotiations in the context of managing export-route risks, while the volume under discussion remains capped at up to 2 million tonnes a year from Train 6. The parties’ next step is to continue negotiating the purchase alongside the project’s ongoing permitting and development procedures. The report does not include a date for announcing an agreement or a schedule for gas deliveries.