33-Megawatt Unit at Cape Station Begins Commercial Operations Ahead of Contractual Deadline

By

Key Facts

1The 33-megawatt GeoBlock 1 unit is performing in line with expectations for production and power delivery under a power purchase agreement.
2The facility synchronized with the grid on September 24, 2026, and Fervo announced commercial operations on September 30, one day before the contractual deadline.
3The first phase comprises about 100 megawatts across 3 units, with the two remaining units targeted to begin operations by January 1, 2027.
4The next phase has a capacity of 400 megawatts and is expected to begin operations in 2028.
5The Google agreement covers a 396-megawatt project and 15 years of power delivery, with targeted commercial operation dates beginning in the third quarter of 2028.

Fervo Energy announced that the first unit of its Cape Station project in Utah has entered commercial operations, beginning to generate revenue under a power purchase agreement. The company said the unit, named GeoBlock 1, is performing in line with expectations for production and electricity delivered under the agreement. Commercial operations followed the facility's synchronization with the grid on September 24, 2026; the company then announced the start of operations on September 30. This came one day before the contractual deadline for the start of operations. The unit is the first part of a broader enhanced geothermal energy project that the company aims to develop in phases.

GeoBlock 1 has a capacity of about 33 megawatts and is one of three units in the project's first phase. The company estimates the total capacity of this phase at about 100 megawatts. In June 2025, it announced that the first phase would provide this capacity starting in 2026, while the second phase would add 400 megawatts by 2028. The first unit's start of commercial operations puts the project into the power delivery phase under the agreement, following a focus on developing the planned capacity. Fervo continues work on the other two units in the first phase, targeting commercial operations by January 1, 2027.

Fervo said GeoBlock 1 is performing in line with expectations for production and electricity delivered, linking operational performance to the obligations under the power purchase agreement. The company said the first phase is divided among three units, while the two remaining units have not yet entered commercial operations. Under the announced timeline, completion of the first phase depends on bringing them online before the start of 2027. The next phase will add 400 megawatts and is currently under construction, according to the company, with operations expected to begin in 2028. Cape Station therefore includes units that have begun commercial operations and others still under development, on a schedule extending through 2028.

On the contracting side, Fervo signed an agreement with Google for a 396-megawatt enhanced geothermal energy project at Cape Station. The agreement provides for power delivery over 15 years in four successive tranches of 99 megawatts each. The targeted commercial operation dates for these portions begin in the third quarter of 2028, according to the company's filing with the U.S. Securities and Exchange Commission. This schedule differs from that of GeoBlock 1, which entered commercial service in September 2026. The agreement shows that the project's contractual commitments extend beyond the start of operations at the first-phase units, with the targeted dates for later tranches still set for 2028.

Fervo announced in June 2025 that it had secured $206 million in additional capital to develop Cape Station. At the time, the company outlined a plan beginning with a first phase with capacity of 100 megawatts from 2026, followed by a second phase adding 400 megawatts by 2028. GeoBlock 1's start of commercial operations is part of the first phase described in that earlier plan, while the company continues work on the two remaining units. The company says the next phase, with capacity of 400 megawatts, is under construction and is expected to begin operations in 2028. These phases provide the timeline for the transition from the unit that has entered operations to the additional capacity planned for the project.

In an update published on November 5, the company said its system had recorded 167 yellow-level seismic events and three red-level events since stimulation began at Cape Station. It reported that the three largest events occurred in September, with readings ranging from 2.6 to 3.3, depending on the monitoring networks used. It also said records from the University of Utah and the U.S. Geological Survey recorded values of between 2.6 and 3.1 for the same events. The company places these figures in the context of its monitoring of seismic activity at the site since February 2024. Among the upcoming dates announced by Fervo is an investor open house at Cape Station on November 19, 2026, offering a chance to visit the site and speak with the company's team without formal presentations.