Hallador Raises Forward Sales 26% to $3 Billion in Third Quarter
Key Facts
Hallador Energy said on Nov. 9 that the value of its contracted forward sales rose 26% from the second quarter to $3.0 billion, reflecting electricity supply agreements the company signed during the year. The company said the total includes the effect of two agreements signed on Oct. 7, so it represents a forward sales book, not revenue earned during the quarter. The announcement coincided with third-quarter results, which showed operating revenue of $130.3 million. Revenue increased from $101.5 million in the prior quarter but remained below the $146.6 million recorded a year earlier. The results highlight expanding future commercial commitments alongside lower year-over-year revenue and cash performance in the quarter.
The company reported a net loss of $4.5 million in the three months ended Sept. 30, 2026, compared with net income of $23.9 million in the same period of 2025. Operating cash flow was negative $21.8 million, compared with positive cash flow of $23.2 million a year earlier. On adjusted earnings before interest, taxes, depreciation and amortization, Hallador reported $17.3 million, compared with an adjusted loss of $2.9 million in the second quarter and earnings of $24.9 million a year earlier. The comparison shows improvement from the prior quarter on this measure, while remaining below the year-earlier level. The quarter therefore presented a mixed picture, with adjusted performance improving sequentially while net income and operating cash flow declined year over year.
Operationally, generation at the Merom plant rose 77% from the second quarter to about 1.4 million megawatt-hours in the third quarter, following the completion of major planned maintenance in July. Hallador said the three major supply agreements for the Merom plant that it signed during 2026 increased its forward sales book, with the latest signed in October. Each of the three agreements priced energy and capacity at more than $80 per megawatt-hour, according to the company. The quarter’s increase in generation provides operational context for the rise in contracted sales, while the announcement attributed part of the increase to the new agreements. In its second-quarter results, the company reported $1.8 billion in contracted revenue from delivered energy, accredited capacity and coal sales to third parties as of June 30, 2026.
For the Turtle Creek project, the CEO said management’s goal is to double an investment of about $800 million to a value of $1.6 billion within 24 months. That remains a stated value target, not a value realized by the project. The company plans a natural gas-fired power plant with capacity of about 460 megawatts in Sullivan County, Indiana, to be owned and operated by Turtle Creek Gas. Hallador expects commercial operations to begin in the second half of 2028. The company said the turbine and generator equipment it purchased has been exported and is on its way to the United States, ahead of the transportation, refurbishment and logistics work required for the project.
The financial data show that project financing adds significant commitments to the company’s balance sheet. In September 2026, Hallador entered into a credit facility of up to $600 million, including an initial $550 million loan funded that month and a $50 million delayed-draw commitment designated for the Turtle Creek project. The delayed draw remains available through Sept. 15, 2027, under the financing terms. The company also estimated additional transportation, refurbishment, insurance and logistics costs for the equipment at about $100 million. Total debt rose to $551.9 million on Sept. 30 from $45.0 million on June 30, following the close of a new construction financing facility and refinancing of existing debt. Meanwhile, total liquidity was $103.2 million at the end of September, compared with $84.2 million at the end of June and $46.4 million a year earlier.
Hallador is targeting a final investment decision on the Turtle Creek project before the end of 2026, while keeping commercial operations targeted for the second half of 2028. The company said the grid connection study conducted by market operator MISO was completed under its expedited resource addition study program, but the final interconnection agreement has not yet been signed, and the company is working to complete it. The outstanding agreement is a pending step before the company proceeds with its targeted investment decision. HNRG closed at $10.1 on Nov. 6, 2026. The announcement thus reflects two parallel tracks: growth in the electricity sales book and continued work on project requirements and financing ahead of the targeted decision date.