StocksMedium•11 November 2026•
4 min read

Fortuna values Diamba Sud project at $397.5 million, ties construction to permits

By

Key Facts

1The feasibility study estimated initial capital for the Diamba Sud project at $397.5 million.
2Senegal issued notice that the exploitation license application had been accepted on November 2, 2026, after the process began in February 2026.
3Detailed plant design was 15% complete, accommodation camp preparation was 80% complete, and civil works at the camp were 40% complete.
4Fortuna targets pouring first gold during the second and third quarters of 2028, subject to the stated conditions and schedule.
5The feasibility study estimated average annual production of 158,000 ounces during the first four years and 116,000 ounces over the mine's 9.4-year life.

Fortuna Mining estimated initial capital for development of its Diamba Sud gold project in Senegal at $397.5 million, according to the feasibility study issued in June 2026. In an update issued on November 2, the company said full construction remains conditional on obtaining the exploitation license, board approval of the final investment decision and completion of local customary approvals for construction work. Senegal's Ministry of Mines and Geology issued notice on November 2 that the license application had been accepted, after the application process began in February 2026. Fortuna expects the government's internal review of the final license to be completed during the fourth quarter of 2026. This puts the project at an advanced stage of preparation, but does not mean full construction has begun.

The company said early works include completing preliminary engineering design, with detailed design of the processing plant 15% complete. Earthworks and grading at the new accommodation camp were 80% complete, while civil works there were 40% complete, according to the November 2 update. Fortuna said it had issued purchase orders and made advance payments for long-lead equipment, including the semi-autogenous grinding mill, primary crusher and carbon-in-leach tank panels. The company selected SENET as contractor for engineering, procurement and construction management, and issued it a limited notice to proceed with early works. These steps show progress in preparation, design and procurement ahead of the approvals needed to move into full construction.

Fortuna's announced schedule calls for critical-path construction activities to begin in the fourth quarter of 2026, alongside the final investment decision, subject to permitting and decision conditions being met. The company targets commissioning the processing plant, pouring first gold and beginning the production ramp-up during the second and third quarters of 2028. It said the government expects to complete its internal procedures for the final exploitation license during the fourth quarter of 2026. The company also said the project still requires completion of a new mining convention with Senegal and government approval. Negotiations on the convention are based on Senegal's 2016 Mining Code, with proposed provisions for a ten-year financial stability framework.

The feasibility study estimated after-tax net present value, at a 5% discount rate, at $1 billion, after-tax internal rate of return at 60%, and capital payback at one year, based on an assumed gold price of $3,500 per ounce. The study estimated average annual production of about 158,000 ounces during the first four years, followed by 116,000 ounces a year over the estimated 9.4-year mine life. The estimated project life increased to 9.4 years from 8.1 years in the 2025 preliminary economic assessment. Probable mineral reserves total 20.5 million tonnes at an average grade of 1.75 grams of gold per tonne, equivalent to 1.15 million ounces of gold. Diamba Sud is in the Kedougou region of southeastern Senegal, about 665 kilometres from Dakar.

Fortuna said the higher capital estimate compared with the previous preliminary assessment reflects the inclusion of local content requirements and Senegalese regulations, higher material quantities following engineering progress, the need for additional ground improvements and an expanded project scope. It said the feasibility study estimate is based on more advanced engineering, with major work quantities derived from three-dimensional models and prices for major mechanical equipment based on quotations. The project received the environmental decree approving its environmental and social impact assessment, according to the company's announcement on June 15, 2026. Fortuna has positioned Diamba Sud, alongside the Séguéla mine expansion, within its plan to increase annual gold production by about 60% to an annual rate of 500,000 ounces from mid-2028. Achieving that target remains dependent on executing both projects on the announced schedule and completing the required approvals.