1Consolidated net profit was 1,652 crore rupees in the second quarter of fiscal 2027, up 33% year on year.
2Profit before exceptional items was 1,521 crore rupees, up 22%; net exceptional items after tax were 131 crore rupees.
3First-half revenue was 38,784 crore rupees, and earnings before interest, taxes, depreciation and amortization were 8,494 crore rupees.
4The company approved an investment of 11,871 crore rupees for a 1,800-megawatt pumped-storage project at Shirwata.

Tata Power said on November 11, 2026, that its consolidated net profit reached a record 1,652 crore rupees in the second quarter of fiscal 2027, up 33% year on year. The company said growth came from broad contributions across generation, renewables, transmission and distribution. Revenue rose to 19,886 crore rupees from 15,769 crore rupees in the year-earlier period, an increase of 26%. Earnings before interest, taxes, depreciation and amortization were 4,245 crore rupees, up 5% from 4,032 crore rupees a year earlier. “We have achieved the highest quarterly profit in our history, with strong contributions from all businesses,” said Praveer Sinha, CEO and managing director.

Net profit before exceptional items was 1,521 crore rupees, up from 1,245 crore rupees in the second quarter of fiscal 2026, an increase of 22%. Net exceptional items after tax totaled 131 crore rupees during the quarter. The difference between the growth rates for reported profit and profit before these items shows that the latter rose at a slower pace, while both measures remained higher year on year. The company presented the results as the product of broad growth across its businesses, rather than the performance of a single segment. It also said regulated and long-term contracted businesses now account for a larger share of earnings before interest, taxes, depreciation and amortization, providing flexible cash flows.

For the first half of fiscal 2027, the company reported revenue of 38,784 crore rupees, up 17% year on year, and earnings before interest, taxes, depreciation and amortization of 8,494 crore rupees, up 7%. Capital expenditure was about 10,000 crore rupees over the six months, the company’s highest half-yearly spending, directed toward renewables, transmission, storage and grids. Tata Power added 765 megawatts of clean and green generation capacity in the first half, bringing its total installed capacity from these sources to 8.6 gigawatts. The company said the expansion of its renewables business was also supported by capacity additions of 1.4 gigawatts over the preceding twelve months. In distribution, commercial and technical losses in Odisha fell to 21.0%, an improvement of 5.7% compared with the first quarter of fiscal 2027.

The company attributed part of the strength in first-half demand to industrial and agricultural activity and higher household consumption, while heat waves and delayed monsoon rains contributed to increased cooling consumption. In conventional generation, it said Mundra maintained operational availability of 89% in the second quarter under the extended Section 11 directive. The company added that the plant is operating at full capacity under the directive through the end of December 2026. It included this operational contribution in a quarter that, it said, also benefited from renewables, transmission and distribution. In solar manufacturing, the company’s businesses produced 0.9 gigawatts of cells and 1 gigawatt of modules during the quarter, with module yields at 97%.

The board approved an investment of 11,871 crore rupees to add a 1,800-megawatt pumped-storage project at Shirwata in Maharashtra. The company set a 51-month timeline to add the proposed capacity, according to the disclosure announced on November 11, 2026. The project will be financed with 75% debt and 25% equity. The company said pumped storage supports the use of renewable energy around the clock and allows power to be shifted between periods of generation and demand. The project is alongside 4.9 gigawatts of renewable capacity under construction or in the pipeline, and battery storage systems with a capacity of 696 megawatt-hours.

In a management change, the company appointed Sanjay Banga as an additional director and CEO-designate effective November 11, 2026. He is scheduled to take over as CEO and managing director for a five-year term starting May 1, 2027, subject to shareholder approval. The leadership transition will therefore begin before the new term takes effect in May. The announcement coincided with first-half results that combined revenue and profit growth with high capital expenditure. The Mundra plant, under the directive extended through the end of December, and the energy and storage projects for which the company set timelines remain the key upcoming operational developments cited in its disclosures.