1The department closed its first loan to support domestic oil and natural gas production on November 10, 2026.
2The Elkhorn project includes upgrading 22 offshore platforms off Louisiana.
3At peak production, the project is expected to add up to 38,600 barrels of oil and 77 million cubic feet of natural gas per day.
4The department expects 2,400 construction-related jobs and 400 operational jobs.
5The department estimates additional federal government royalties of about $1.6 billion over the project’s lifetime.

The U.S. Department of Energy said on November 10, 2026, that it had closed the first loan in its history to support domestic oil and natural gas production, financing Arena Energy’s Elkhorn project in the Gulf of America. The department said the project would increase peak production by up to 38,600 barrels of oil and 77 million cubic feet of natural gas per day. The work includes upgrading 22 offshore platforms off the Louisiana coast, in the Gulf of America shelf area. The official project profile places it in the Eugene Island area, while industry coverage identifies its scope as the Southern Eugene Island area. The loan thus links the rehabilitation of existing offshore assets with an expected increase in production from energy suppliers. Energy Secretary Chris Wright said, "The Elkhorn project will increase oil production by up to 38,600 barrels per day and provide thousands of jobs."

The project scope includes returning idle platforms to service, as well as expanding production and water-handling capacity at active facilities, according to Offshore magazine. It also includes building new subsea gas pipeline infrastructure to connect future wells to existing pipelines. The department says Arena currently produces about 30,000 barrels of oil per day offshore. At the project’s peak, the maximum expected increase in oil would exceed that current level, alongside the expected daily addition of gas. The department’s statement estimates that over its lifetime the project will add about 125 million barrels of oil and 250 billion cubic feet of natural gas to U.S. production. These estimates link upgrades to platforms and infrastructure with cumulative production over the project’s lifetime.

The department expects the project to support 2,400 construction-related jobs and 400 operational jobs. It also estimates that increased production will generate about $1.6 billion in additional royalties for the federal government over the project’s lifetime. The department presented these figures among the project’s expected economic impacts, alongside its oil and gas production estimates. Wright referred in his statement to providing "thousands of jobs," while the department’s estimates break the total down between construction-related and operational jobs. The department describes the United States as the world’s largest producer and exporter of oil and natural gas. According to its statement, the project is part of efforts to support domestic production by financing upgrades to existing Gulf infrastructure.

The project is in a region that remains an important source of U.S. offshore oil. Federal offshore crude oil production in the Gulf of Mexico averaged 1.77 million barrels per day in 2024, according to the U.S. Energy Information Administration. In a forecast issued in June 2025, the agency estimated an average of 1.80 million barrels per day in 2025 and 1.81 million in 2026. The agency estimated at the time that the region would account for about 13% of U.S. crude production and about 1% of marketed natural gas production in 2025 and 2026. It also projected that 13 fields would begin production during those two years, and said Gulf output could decline without those new fields. Those figures are the agency’s forecasts published in June 2025, while the Elkhorn project adds upgrades to existing assets and gas pipeline infrastructure.

Arena said the financing closed after completion of the technical, legal, environmental and financial due diligence required under the Energy Department’s loan program. The company added that it would carry out the project with its two affiliated partners, White Fleet Drilling and Rosefield Pipeline. The execution plan combines returning idle platforms to service, expanding the capabilities of active facilities and laying new gas pipelines. This work provides the practical framework for meeting the production targets announced by the department, including the expected daily increases in oil and gas at peak output. The maximum production estimate remains tied to the peak phase, while the cumulative production and royalties estimates reflect the project’s lifetime. The department announced the loan closing on November 10, while Arena outlined the implementation steps and participating partners.