StocksMedium•11 November 2026•
4 min read

Montage Gold Produces 23,462 Ounces in October as Plant Runs at 104% of Capacity

By

Key Facts

1October gold production was 23,462 ounces, bringing total production since the first pour to 24,746 ounces through the end of the month.
2The oxide circuit processed about 880,000 tonnes in October, and the plant operated at an average of more than 90% of its nameplate capacity of 11 million tonnes a year, reaching 104% in the final week.
3The average grade of ore processed was 0.82 grams of gold per tonne, and average gold recovery was 95% in October.
4The company is targeting a declaration of commercial production for the oxide circuit in the fourth quarter of 2026 and completion of the hard-rock circuit in the second quarter of 2027.

Montage Gold produced about 23,462 ounces of gold in October from its Koné mine in Côte d’Ivoire, after the plant reached 104% of nameplate capacity in the final week of the month, according to the company’s third-quarter activity report published on November 11. The company said the oxide circuit processed about 880,000 tonnes of ore during October, and the plant operated at an average of more than 90% of its nameplate capacity of 11 million tonnes a year. Total production since the first gold pour stood at 24,746 ounces through the end of October, excluding gold inventory in the processing circuit. The report reflects the project’s transition from construction to operation of the oxide circuit, while work to complete the hard-rock circuit continues. The company is targeting a declaration of commercial production for the oxide circuit in the fourth quarter of 2026.

The average grade of ore processed rose to 0.82 grams of gold per tonne in October, while average gold recovery was 95%, according to the report. The operating metrics table showed the mine milled 475,000 tonnes and produced 1,284 ounces in September, compared with 888,000 tonnes and 23,462 ounces in October. The report points to an increase in ore processed and production between the two months as operations advanced. Montage announced on September 27 that the first gold pour had taken place the previous day, September 26, at the Koné mine. The first pour yielded about 1,140 ounces, after more than 400,000 tonnes of ore had been processed since it began entering the oxide circuit on September 8.

The first gold pour came ahead of the initial schedule, which targeted the second quarter of 2027, and the company said it was achieved on budget and ahead of schedule. Montage had expected the oxide circuit to reach commercial production in the fourth quarter of 2026, with completion of the hard-rock crushing and milling circuit in the second quarter of 2027. In its latest report, the company reaffirmed that a declaration of commercial production for the oxide circuit remains targeted for the fourth quarter of 2026, and that work on the hard-rock circuit is on schedule for completion in the second quarter of 2027. These dates provide context for current operational progress, with the oxide circuit operating while work on the circuit designed for hard rock remains underway. The company said the Koné mine had become Côte d’Ivoire’s ninth operating gold mine.

Capital committed to building the project totaled about $796.4 million as of November 11, or nearly 90% of estimated total capital expenditure of $885 million, Montage said. The committed amount was $753.6 million at the end of the third quarter, of which $725.2 million had already been spent. Available liquidity stood at $205.6 million on September 30, compared with $309 million on June 30. These figures track spending and funding alongside the start of gold production and the continuation of construction work. The company says operation of the hard-rock circuit is scheduled for completion in the second quarter of 2027.

On exploration, Montage said 122,570 metres had been drilled at Koné during the first nine months of 2026, as part of an annual program targeting 130,000 metres. The company had expected further results from the drilling program in the fourth quarter of 2026. It also expected mining to ramp up at the higher-grade Gbongogo Main deposits in late fourth-quarter 2026, with mining at other satellite deposits to begin during 2027. The updated feasibility study published in 2024 estimated the mine’s life at about 16 years, with annual production exceeding 300,000 ounces during the first eight years. The company expects operations to provide about 1,500 permanent jobs once fully developed, after the project created about 3,600 construction jobs, more than 95% of which went to nationals.