200 MW Minimum Power Supply for New Era’s Texas Data Center Project

By

Key Facts

1The power agreement provides for at least 200 MW and up to 207 MW from the 1,180 MW Odessa facility, other available sources or the Texas grid.
2The company deposited $118 million in cash collateral to support the letter of credit associated with the power agreement.
3Third-quarter revenue was $147,674 versus $159,411, and the company reported a net loss of $16,599,408 versus $5,783,173.
4The company is in advanced negotiations over a Phase I lease under a non-binding letter of intent covering Phases I and II.

New Era Energy & Digital announced its third-quarter results on 12 November 2026, alongside an update on its Texas data center project and the power agreement securing the needs of its first phase. The agreement with Luminant, a Vistra subsidiary, provides for the supply of at least 200 MW and up to 207 MW. The company said the power would come from the 1,180 MW gas-fired Odessa facility, other available sources or the Texas power grid. The agreement gives the project a defined range of contracted power, but does not by itself settle the site’s commercial path. The company is still negotiating Phase I lease documents with a prospective tenant, according to its statement accompanying its filing with the U.S. Securities and Exchange Commission.

The lease negotiations are based on a non-binding letter of intent covering Phases I and II with the same prospective tenant. The company said it was in advanced negotiations over Phase I documents, but did not announce the signing of a binding lease in its 12 November statement. This means the announced power arrangements are advancing alongside a commercial process that has not yet reached a final agreement to lease the project. According to the company’s disclosure, the initial 20-year power purchase agreement term begins with the first delivery of power. The agreement includes successive automatic one-year renewals unless either party gives notice of non-renewal.

The company linked support for its power agreement obligations to cash collateral, saying in its 12 November investor presentation that it had deposited $118 million to support the letter of credit associated with the agreement. This puts the letter-of-credit collateral among the project’s financing needs, alongside the supply arrangements themselves. Luminant’s obligations are subject to conditions precedent that must be satisfied by 31 December 2027. The conditions include signing an agreement to buy and sell the substation and related equipment, according to the company’s disclosure on the power agreement. The fulfillment of the supply obligations therefore remains tied to completing the conditions specified in the agreement, as well as progress in the lease negotiations.

Third-quarter results showed a divergence between revenue and losses compared with the same period a year earlier. Revenue was $147,674 in the quarter ended 30 September 2026, compared with $159,411 in the third quarter of 2025. Net loss was $16,599,408, compared with a net loss of $5,783,173 a year earlier. Benzinga, meanwhile, reported that the company’s revenue exceeded the analyst estimate it cited, of $50,000, coming in at nearly three times that level. The site said the per-share loss was larger than expected, while the stock rose after the results were announced.

The company’s stock, trading under the ticker NUAI, closed at $2.33 on 11 November 2026, according to EL7 data. The results update and the company’s project announcement came the following day, 12 November. The investor presentation also showed the number of shares outstanding rising from 106,490,928 on 30 June 2026 to 140,569,465 on 6 November. The table includes the issuance of 23,272,727 shares in a private placement during the period, according to the presentation. These figures put the change in the share count in the context of financing that preceded the company’s update, without specifying its effect on each shareholder’s stake.

The project timeline extends to Phase II, with the investor presentation expecting delivery of its turbines between the fourth quarter of 2027 and the first quarter of 2028. This schedule places the Phase II turbines after the power availability date associated with Phase I in the supply agreement. The initial 20-year term of the power purchase agreement begins with the first actual delivery, not simply with its announcement. Luminant’s conditions precedent remain due by 31 December 2027, while the company’s advanced negotiations over Phase I lease documents continue under a non-binding letter of intent covering both phases. Completing those conditions and reaching a final lease agreement will be among the next milestones in the project path outlined by the company.