Fermi Announces Agreement to Develop 600 Megawatts at Matador Project Starting in 2027
Key Facts
Fermi announced on Nov. 12 an agreement with an unnamed hyperscale computing company to develop an initial 600 megawatts of capacity at the Matador project in Texas, with development set to begin in 2027. In its filing with the U.S. Securities and Exchange Commission, the company said the arrangements include a $200 million upfront payment and a $15 million agreement for early construction work and site preparation. However, the announced agreement is a nonbinding letter of intent and remains subject to negotiation and execution of definitive documents. Fermi added that the parties are working to finalize a long-term lease. The company’s shares closed at $2.06 in the Nov. 12 session, according to EL7 data.
Fermi is seeking to convert the preliminary agreement into a contract that would allow development of the project’s capacity to begin, but that depends on completing the contractual terms. The company said it and the customer are working to finalize a $90 million agreement to purchase structural steel and construction materials. It did not disclose the customer’s name, describing it as an investment-grade hyperscale computing company. Chief Executive Lee McIntyre said converting its pipeline of prospective customers into leases could fill the company’s current capacity of 2.2 gigawatts. He added that large hyperscalers want sites with authorized power ready for connection, and that Matador is among the few sites currently able to meet that demand.
The new agreement follows Fermi’s termination of its lease and services agreement with TensorWave, signed in August 2026. The deal’s closing deadline passed on Oct. 31 without an extension, and Fermi terminated the agreement on Nov. 10. The company said the related credit support agreement with AMD also ended. It reported that terminating the TensorWave agreement did not affect its financial statements for the quarter ended in September. That makes completing the new lease and finalizing the arrangements a pivotal step for the project.
Fermi remains in the development stage with no revenue and recorded $142.2 million in general and administrative expenses in the third quarter of 2026. The expenses included $65.8 million in noncash stock-based compensation, as well as $21.5 million in financial advisory fees settled through the issuance of shares. Cash and restricted cash totaled $315.5 million on Sept. 30, against net outstanding debt of $958.4 million. The company also invested $133.4 million in property, plant and equipment during the quarter, bringing its net balance to about $1.67 billion. Operating activities used $110.554 million in the nine months ended Sept. 30, 2026, compared with $8.291 million in the corresponding period of 2025.
Progress on the first phase is tied to financing and development deadlines set out by the company in its filing. Fermi must complete committed financing by Feb. 10, 2027, together with any shares required, sufficient to fund at least 400 megawatts of generation capacity. Vertical construction at the site also requires a notice to proceed from the Texas Tech University System by Dec. 31, 2026. One condition for that notice is a lease for a first-phase tenant with capacity of at least 200 megawatts. The company had announced that its third-quarter earnings call was scheduled for Nov. 12 at 9 a.m. Eastern time.