1TVA operating revenues were $10.037 billion for the nine months ended June 30, 2026, compared with $9.758 billion a year earlier.
2TVA revenue from local power companies rose 2.5% to $9,001 million for the nine months ended June 30, 2026.
3PowerCompute said the new TVA tariff charge is about $1.5 million per megawatt above the first 5 megawatts of contracted demand.
4TVA’s plan estimates a need to add between 11 and 32 gigawatts of generating capacity by 2040.

I was unable to verify the capacity commitment charge agreement attributed to the Tennessee Valley Authority (TVA), or its value and terms, in an open official or credible news source. The authority’s page for its Nov. 10, 2026, board meeting did not mention the alleged agreement. At the meeting, held in Knoxville, the board reviewed fiscal 2026 achievements, including progress in new generation, system reliability, financial discipline and customer programs. Board Chairman Mitch Graves said priorities included keeping electricity affordable and maintaining system reliability. He added that the authority was seeking to prepare to meet growth in the region’s energy needs.

Available financial results for the prior period show growth in the authority’s revenues, but do not establish details of the reported agreement. Operating revenues were $10.037 billion for the nine months ended June 30, 2026, compared with $9.758 billion in the corresponding period of 2025. TVA said the revenue increase was mainly related to higher fuel-cost recovery rates and increased sales volume. The authority attributed part of the increase in sales volume to the data processing, web hosting and related services sector. Revenue from local power companies rose to $9,001 million, from $8,782 million in the corresponding period, an increase of 2.5%.

Total operating expenses, meanwhile, rose $48 million during the nine months ended June 30, 2026, compared with the same period of 2025. TVA said higher natural gas prices contributed to increased fuel and purchased power expenses. It also said increased generation by the authority partly reduced purchased power expenses. These results show some of the effects of fuel costs and demand on the authority’s accounts during the period, without confirming the terms of a new charge or how it would be allocated to customers. Revenue from local power companies remains an indicator of sales growth across the authority’s network during the stated fiscal period.

In a separate tariff announced for companies, PowerCompute said TVA’s new charges began with fiscal 2027 on Oct. 1, 2026. According to the company, the capacity commitment charge is about $1.5 million per megawatt for new or expanded data center loads above the first 5 megawatts of contracted demand. PowerCompute announced on Oct. 6 that its site contract in Columbus, Mississippi, increased contracted capacity from 8.5 to 11 megawatts and took effect on Oct. 1. The company said the site did not incur the new capacity commitment charge. This statement provides details about the tariff and exemption threshold as presented by PowerCompute, but does not document the agreement attributed to TVA in the reported account.

The authority’s generation plans put demand growth in the context of the need for additional resources. TVA’s 2026 integrated plan estimates a need to add between 11 and 32 gigawatts of generating capacity by 2040. The plan recommends expanding dispatchable resources, including natural gas and storage, to meet immediate needs. The authority also says it plans to add more than 6,200 megawatts of new capacity, with about 3,770 megawatts currently under construction. Separately, PowerCompute’s statement says the fiscal 2027 allocation includes 2,000 megawatts of available capacity, allocated on a first-come, first-served basis.