CryptoMediumUpdated×2•Originally published 13 November 2026•Updated 14 November 2026•
4 min read

Paraguay Grants Data Center Power Contract of Up to 286 Megawatts for 15 Years

By

Key Facts

1The ANDE-Kuntur contract runs for 15 years, with maximum capacity of 286 megawatts.
2Supply starts at 6 megawatts on December 1, 2026, rises to 146 megawatts on April 1, 2028, then reaches 286 megawatts in April 2029.
3The average tariff is $56.39 per megawatt-hour at 23 kilovolts and $48.91 at 220 kilovolts.
4Existing cryptocurrency mining companies’ contracts expire on December 31, 2027.

Paraguay’s state-owned electricity company ANDE and Kuntur S.A. signed a 15-year power supply contract for capacity that will gradually rise to 286 megawatts in April 2029, according to a company statement published on October 23, 2026. Supply will begin on December 1, 2026, at 6 megawatts, before rising to 146 megawatts on April 1, 2028, RCC reported. ABC Color described the contract as serving the Iguazú AI City project in Yguazú and linked Kuntur to Araico. The agreement puts the data center’s demand for electricity at the center of debate over how available capacity should be allocated between advanced technology projects and energy-intensive activities. It comes as existing cryptocurrency mining companies’ contracts expire on December 31, 2027, ABC Color reported, citing ANDE.

The contract tariff, according to ANDE’s statement, provides for an average of $56.39 per megawatt-hour at 23 kilovolts and $48.91 per megawatt-hour at 220 kilovolts. RCC said the tariff will be updated annually in line with the U.S. inflation index, with a minimum annual increase of 2.5%. The mechanism also includes a technical review every two years linked to changes in the company’s average generation cost. These terms cover the contract’s long duration, alongside the increase in supply from 6 megawatts at the outset to 146 megawatts in April 2028 and then 286 megawatts in April 2029. The stages show that the project’s contracted capacity will expand in increments, while the published tariff varies by voltage level.

The new tariff category was established under resolution P/N.º 52552/2026 and covers electricity-intensive industries using advanced technology at 220, 66 and 23 kilovolts, according to ANDE. Kuntur fully financed the infrastructure work required to connect to the Yguazú substation, with that work later to become assets of the state-owned company, RCC reported. The resolution distinguishes the advanced technology category, which includes the data center project, from the description sources have given of existing mining contracts. The private company’s financing of the connection work gives the agreement a structural dimension beyond the purchase of electricity, as the infrastructure will pass to ANDE once built. This comes as multiple projects compete for capacity that press coverage says is limited compared with recorded requests.

ABC Color reported in October 2026 that ANDE had capacity requests of 6,000 megawatts, against 750 megawatts available, and that 286 megawatts of the available capacity had been allocated to Kuntur, according to the company’s president. Earlier, the newspaper reported in February 2025 that demand from mining facilities stood at 435 megawatts, with contracted demand expected to reach 935 megawatts by the end of that year. The mining figures remain tied to the period in which they were announced, while the available capacity and request figures reflect the picture reported by the newspaper in October 2026. The gap between recorded requests and available capacity puts electricity allocation at the heart of debate over new contracts. That shortfall places the Kuntur contract within a wider discussion of project priorities and supply terms.

According to ABC Color, ANDE’s Association of Engineers proposed allocating capacity through sealed bids for energy-intensive companies and estimated that allocating 700 megawatts at $60 per megawatt-hour could add about $98 million a year to the company’s revenue. This is an estimate in the association’s proposal, not an approved contract. The proposal provides for the first 200 megawatts allocated to receive non-interruptible supply, while capacity above that could be subject to contracts allowing supply to be reduced for up to 300 hours. ANDE’s president also said, according to the newspaper, that 40 other projects have memorandums of understanding and that their assessment would take energy availability into account. These proposals open a path for debate over electricity allocation after existing mining contracts expire in December 2027.

At the system consumption level, ANDE said total electricity consumption reached 29,419 gigawatt-hours in 2025 and peak demand was 5,280 megawatts on December 15 of that year. The company expects demand by 2043 to reach 11,009 megawatts of capacity and 57,561 gigawatt-hours of energy a year. It said its plans include strengthening transmission and generation, as well as alternative solutions to meet this trajectory. These projections place Kuntur’s 15-year contract within a broader horizon of rising electricity needs, as competition for currently available capacity intensifies. The allocation of supply to other projects remains tied, according to ABC Color’s account of the company president’s remarks, to energy availability at the time of their assessment.