1AWS's combined investments in the New Carlisle, Hobart and Wheatfield sites total $33 billion.
2AWS plans to pay $98 million in taxes upfront and provide $700 million over 30 years.
3The associated gas generation facilities are expected to begin commercial operation during 2030.
4GenCo is developing two battery storage systems with capacities of 400 and 100 megawatts.

Amazon Web Services has begun construction on a data center project in Wheatfield, Indiana, as part of investments that Data Center Dynamics says total $33 billion across the New Carlisle, Hobart and Wheatfield sites. The outlet reported on November 16, 2026, that work had started, with contractor Ryan Companies carrying it out over several years. Scott Eckhardt, AWS economic development official, described the project as "one of the largest private-sector investments in Jasper County." The start of construction places the new site within the company's expansion in the state, while the report does not specify when the data center will begin operating. The announced total covers all three sites, without breaking out Wheatfield's share.

The project plans a campus that could include up to 9 buildings on a 304-acre parcel sold to AWS by NIPSCO, according to Data Center Dynamics. The Schahfer power station is about half a mile from the site. The report said the cooling design relies mainly on air, with water used for cooling on about 2% of days each year, during the hottest days. These details provide a picture of the site's scale and announced design, as well as its proximity to an existing generation facility. The report gave no timeline for the campus to begin operating and no separate figure for Wheatfield's value.

Data center construction is accompanied by the development of electricity generation and storage infrastructure in the area. In its filing with the Securities and Exchange Commission, NiSource said site work includes extensive preparation and grading and the civil work needed to support construction of a power unit. The company said gas generation facilities associated with the Amazon Data Services contract are expected to begin commercial operation during 2030. Its subsidiary GenCo is also developing two battery storage systems with capacities of 400 and 100 megawatts, and said mobilization had begun and work at the site was under way. The report did not specify when the data center itself will begin operating.

Locally, Data Center Dynamics said AWS will pay $98 million in taxes upfront and provide contributions of $700 million over 30 years. The company's agreement with NIPSCO, according to a decision by the Indiana Utility Regulatory Commission, also provides for expected savings of nearly $1 billion for existing customers through bill credits over 15 years. Those savings are tied to the customers' contract with the utility, while the taxes and contributions represent local commitments associated with the project. Against the backdrop of AWS's expansion in the state, the company announced in April 2024 a plan to invest $11 billion in a data center near New Carlisle, with at least 1,000 new jobs expected. The Associated Press reported at the time that a local official expected construction there to extend over the following decade, while the announcement did not include a project timeline.

In the regulatory process, Amazon Data Services requested a new construction permit and a Part 70 operating permit from the Indiana Department of Environmental Management for a site in Wheatfield. The department said the proposed permit, if approved, would allow the company to build and operate a new data center. The notice record showed that the public comment period on the draft permit ran from September 24 to November 16, 2026. A virtual hearing was also scheduled for November 10. The proposed permit remains part of the site's regulatory process alongside the start of construction.

Amazon shares closed at $257.75 in the November 16, 2026, session, according to EL7 data. In a separate project within the company's Indiana expansion, the New Carlisle plan announced in 2024 paired a planned investment of $11 billion with expectations of at least 1,000 jobs. Across the three sites, the total investment reported by Data Center Dynamics is $33 billion, with no breakdown among New Carlisle, Hobart and Wheatfield. In the energy sector linked to the site, NiSource identified 2030 as the expected start of commercial operation for the gas generation facilities. Construction of the Wheatfield project is expected to take several years, according to the report.