Golar LNG allocates $2.45 billion for fourth unit with capacity of 3.5 million tonnes a year
Key Facts
Golar LNG estimated the total budget for its fourth floating liquefied natural gas production unit at about $2.45 billion, for a project with capacity of 3.5 million tonnes a year and a planned delivery date in 2029. The company said in its earnings release that the budget includes the donor vessel, supervision at the construction yard, spare parts, crew training and contingencies, as well as initial fuel, voyage costs to the operating site and final commissioning. The company took the final investment decision on the project during the third quarter, on August 12, and reaffirmed it with the results announcement on November 18. Golar describes the unit as the nearest available floating liquefaction capacity for delivery in the market. But the project has not yet secured an operating contract, making the securing of a long-term charterer a central factor in the expected return on capital spending.
Management said contracting the fourth unit on terms similar to the Esperanza contract could lift annual EBITDA by about 50% to more than $1.2 billion by 2030, before any potential increase tied to commodity prices. The comparison is based on the revenue base of operating and contracted units; the company expects annual EBITDA from Gimi, Hilli and Esperanza to reach about $800 million by 2028, before commodity gains and inflation adjustments. These figures show that reaching the target depends on securing a contract for the fourth unit and its terms, not simply on the unit entering service. Golar said it is holding detailed discussions on deploying it under a long-term contract. The company did not announce a timeline for completing those discussions or name a potential counterparty.
The investment comes as third-quarter results showed a decline in Golar's metrics compared with the same period a year earlier. Net income attributable to the company was $22.615 million, down 28%, while operating revenues fell 32% to $83.728 million. Adjusted EBITDA declined 33% to $55.809 million. Management attributed Hilli's weaker contribution to the end of its 8-year contract in Cameroon on July 27, before its new contract begins in the second half of 2027. The vessel generated only one month of revenue during the quarter after its previous contract ended.
Hilli completed its Cameroon contract after delivering 156 cargoes and achieving 100% economic availability throughout the eight years, according to the chief executive. The vessel left Cameroon in August and arrived in Singapore in September for modifications estimated to cost about $350 million in total. Golar said it will move to Argentina once the modifications are complete to begin a new 20-year contract with SESA in 2027; it estimated adjusted EBITDA under the contract at about $5.7 billion before commodity gains. The chief executive's comments identify the first half of 2027 as the expected timing for completion of the work and the start of the contract, while the company release cited the second half when describing the contract's start. Hilli's return to service under a long-term contract is part of the company's plans to offset the period in which the vessel generated no revenue.
Golar had funded, through the end of the third quarter, the full $300 million in spending recorded by then on converting the fourth unit from equity. It also said available liquidity was about $2.27 billion after accounting for new bonds, an expansion of Hilli financing and the credit facility available to Esperanza. The company expects an amendment to Hilli's sale-and-leaseback financing to release about $472 million in net liquidity in December 2026, with the possibility of adding up to $240 million during 2027 and 2028, subject to further approvals. These amounts provide a picture of the liquidity sources cited by the company alongside its capital commitments. It also announced a cash distribution of $0.25 per share for the quarter to shareholders of record on November 30, payable on December 9.
The company expanded preparations for the possibility of building a fifth unit, booking long-lead equipment during the quarter that it said was necessary to protect an attractive delivery date after a contract is secured for the fourth unit. The chief executive said compressors and dual-fuel engines face supply pressure as AI data centers expand. He said the company wanted to "lock in some key equipment so we secure a very attractive delivery date for unit No. 5 once a contract for unit No. 4 is secured." Golar says it is committed to ordering no more than one unit on a speculative basis, and is targeting a final investment decision for the fifth unit after securing a long-term contract for the fourth. In premarket trading on the day of the results announcement, GLNG shares were about $41.78, down 0.38% from the previous close of $41.94 on November 17.