British Columbia Court Upholds Cancellation of KSM Start Determination, Orders Deeper Consultation

By

Key Facts

1The court upheld the cancellation of the determination that KSM had substantially started, leaving deep consultation as part of the required reconsideration process.
2Seabridge spent about C$102.3 million on KSM in the third quarter of 2026, compared with C$52.8 million in the same period of 2025.
3Seabridge is targeting completion of the KSM feasibility study by the end of 2027.
4Seabridge shares closed at $25.55 on November 18, compared with $26.28 on November 17.

In November, the Supreme Court of British Columbia upheld the cancellation of the determination that Seabridge Gold’s KSM project had substantially started and required the province to conduct deep consultation with the Tsetsaut Skii km Lax Ha Nation. The ruling returns the case to the regulatory review process, with the Environmental Assessment Office to consider submissions and information provided before the decision-maker reconsiders the determination. The end of the deadline for written submissions does not mark the end of consultation, and no completion date has been set. The timing of the subsequent regulatory decision remains open as procedural steps continue. Meanwhile, the company continues to spend on the project and prepare for the feasibility study.

The case dates back to the environmental assessment certificate the province issued for KSM on July 29, 2014, requiring the project to have substantially started by July 29, 2019. The proposed project is a gold, copper, silver and molybdenum mine combining open-pit and underground mining, about 65 kilometres northwest of Stewart. According to the Environmental Assessment Office, a determination of substantial start is made case by case, with physical development at the site a key consideration and other factors also potentially considered. These criteria give weight to work actually completed at the site as part of the review. Seabridge said the office will accept information on work carried out after the original determination through July 29, 2026, and that it has already submitted information on that work.

According to a Seabridge disclosure, a hearing was held on October 14 to resolve outstanding issues over the wording of the court orders, and the Environmental Assessment Office is to allow the company to respond to the Nation’s submissions. The office will then prepare a report on reconsideration in light of the court’s findings and any relevant new information, and give interested parties an opportunity to review its draft before submitting a recommendation to the decision-maker. These stages are separate from the required deeper consultation, and the disclosure gives no timetable for their completion. This means submissions, responses, the report and the recommendation form a series of steps before reconsideration. The court did not decide in this proceeding whether the original determination was reasonable.

Despite the ongoing review, Seabridge said its fieldwork is complete, including the collection of geotechnical, metallurgical, geochemical and environmental data to support the feasibility study. The company has also made progress on preliminary planning for the mine, processing plant and site infrastructure. It spent about C$102.3 million on KSM during the third quarter of 2026, compared with C$52.8 million in the same period of 2025. The company said it continues to pursue a joint venture agreement with a major mining company with the technical, financial and social capabilities to support the project’s development. It is targeting completion of the feasibility study by the end of 2027.

Infrastructure support work included the completion and commissioning of the Treaty Creek Terminal on August 27, 2026, according to the company’s disclosure. Seabridge also said construction of the 13-kilometre Upper Treaty Creek Access Road was nearing completion by the end of the third quarter. The company began developing an execution plan for the project, along with a plan to engage contractors early in 2027. These works show that technical and execution preparations are continuing alongside consultation and reconsideration. The feasibility study targeted for the end of 2027 remains part of the schedule announced by the company.

In New York trading, Seabridge shares closed at $25.55 on November 18, compared with $26.28 in the previous session, according to EL7 data. The price change coincided with the court ruling, but trading data do not establish that the ruling caused the move. The regulatory matter remains tied to completing consultation, preparing the office’s report and submitting its recommendation before the determination is reconsidered. The available information gave no specific date for completion of these stages. The company continues site work and spending and is pursuing a project partner, while targeting completion of the feasibility study by the end of 2027.