Pitarrilla study values project at $736 million at a silver price of $50
Key Facts
Endeavour Silver announced on November 19, 2026, that it had completed the feasibility study for the Pitarrilla project, estimating an after-tax net present value of $736 million at a 5% discount rate and an after-tax internal rate of return of 16.37%. The base case assumes a silver price of $50 per ounce, according to the company’s filing with the U.S. Securities and Exchange Commission. The announcement moves the project from study preparation to a presentation of its economics and next steps, with regulatory approvals and a board decision still required before any development. The study estimated the initial capital required to develop the project at about $585 million, to be spent over an expected construction period of 30 months. It also estimated cumulative sustaining capital at $119 million over the mine life. These estimates put the required funding alongside the returns expected under the study’s assumptions.
The plan includes an automated underground mine with design processing capacity of 4,000 tons per day. The company says the main permits are in place, but the tailings storage facility permit and other approvals and amendments remain pending. Completing the permit is therefore a key part of preparing for any potential development decision, alongside engineering, procurement planning and project optimization, which the company identified as next steps. The process also includes completing and filing the supporting technical report, while a development decision remains subject to board approval. The company’s statement did not specify when that decision would be made. The feasibility results therefore provide an economic framework for the project, while some conditions for moving to execution remain outstanding.
The study estimated average annual production of about 7.5 million silver-equivalent ounces over a planned mine life of 18 years. Expected average production rises to 7.9 million silver-equivalent ounces a year during the first 5 years of full operation. Planned output includes lead and zinc as well as silver; the plan estimates average annual production of 5.4 million ounces of silver, 13,000 tons of lead and 29,000 tons of zinc. The company presents these volumes as part of a long-life mine concept, with higher production in the first years of operation. These estimates depend on the feasibility study’s assumptions, including a base-case silver price of $50 per ounce. They should also be considered alongside the study’s estimates for initial and sustaining capital.
Field and engineering work documented in the third quarter of 2026 preceded the study announcement. The company said in its disclosure that it spent $6.5 million on costs related to the feasibility study during the quarter. The work included underground ramp and drift development, as well as water, hydrogeology and tailings facility engineering studies. It also drilled 5 holes totaling 991 meters, at a cost of $0.3 million. Exploration drilling was then temporarily suspended to focus on collecting data needed for the study. The work illustrates the activities that preceded the project’s economic assessment.
Endeavour said it expects to fund most of Pitarrilla’s construction through a mix of available cash and cash flow from its operating mines. This approach links project funding to the company’s existing resources and operating revenue, while the study estimates initial capital at about $585 million. The statement did not specify the timing of funding sources or the amount each would contribute. The steps announced after the study include completing the technical report, continuing work on the tailings facility permit and required amendments, and preparing the project for a potential development decision. Final approval for development remains subject to the board. Management is scheduled to discuss the feasibility study results on a call and webcast on November 20, 2026, at 9:00 a.m. Pacific time, corresponding to 11:00 a.m. Eastern time.