EL7 Research · Technology
24 September 2026 · Prices as of the 24 September close
0.63 miles delay fuel for a 2.45 GW project: why did Oracle send a force majeure notice when it does not intend to walk away?
Oracle has sent a force majeure notice to the developer of its giant New Mexico site, not to exit but to defer payments if the site does not enter service in 2028. The sticking point is 0.63 miles of a gas pipeline the state refused to let cross its land, while behind the notice sit $288 billion of data-centre leases that have not yet started on the company's books.
Executive summary
- Oracle has sent a force majeure notice to the developer of Project Jupiter in New Mexico, a unit of Blue Owl Capital, according to Bloomberg, citing people familiar with the matter. Force majeure is a contractual state that excuses a party from performance because of circumstances beyond its control. The purpose of the notice, according to the same account, is not to withdraw from the site but to defer payments if the project stalls and does not enter service in 2028 as planned.
- Both parties say nothing material has changed: Oracle says the project "remains on its planned schedule", and Blue Owl says the notice "does not change the financial commitments" to the project. Even so, Oracle shares opened the 24 September session 5.0% below their previous close and ended it down 3.48%.
- The physical bottleneck is strikingly small: a gas pipeline of about 17 miles, of which the federal government approved 16 miles, while the State Land Office rejected just 0.63 miles. Because of this segment, the pipeline's in-service date slipped from 15 August 2026 to 1 February 2027, and the fuel cells that will power the entire site run on gas.
- The real significance of the notice lies not in a single site but in the class of commitments it belongs to: Oracle discloses $288 billion of data-centre lease commitments that have not yet commenced and are not on its balance sheet, about 6.6 times the lease liabilities recorded there. The notice shows the tool available to the company against any delay in this class: trying to shift the cost of waiting onto the developer, not exiting the contract.
- Bloom Energy does not disclose the value of the Project Jupiter order, and the project is not named in its filings. But its revenue is highly concentrated: 73% of first-half 2026 revenue came from a single unnamed customer, and Oracle obtained more than 2.15 million of its shares through a stock warrant, a right granted by the issuing company to buy its shares at a set price within a set period.
- Bottom line: the immediate cause is local and specific, namely 0.63 miles of state land. But the risk-transfer mechanism the notice revealed is general, and likely to recur at any site where the gas or grid connection is delayed.